Morrow Equipment Company v. VDOT Results in $1,209,949 Settlement

The key issue was that the taking changed the configuration of the owner's parcel so that its modular high rise crane sections could no longer be stored as efficiently. The settlement involved the outright sale of additional land at fair market value which reduced Morrow's damages and reduced VDOT's construction costs by eliminating the need for a large retaining wall.

 

The original offer was $772,224.